In-Situ Technologies

The Alberta oil sands industry has been accelerated by several technological advances.

Read More on Technologies

Projects

Deep Well currently has two Alberta Energy Regulator ("AER") approved thermal recovery projects. For more information on our projects click on the link below.

SAGD Project - Read More
HCSS Project - Read More

Current SAGD Project

Phase 1 of our SAGD Project is to determine the use of SAGD technology in parts of our reservoir and to confirm commercial viability of using SAGD technology. Our project operations to date have consisted of drilling the first SAGD well pair, Procurement of equipment and the construction of a facility for steam generation were all successfully completed in early 2014. First steam injection began in May of 2014 with first oil production commencing on September 16, 2014.

Read More     Drone aerial view video

Photo Gallery

Photo gallery of our operations in the Peace River Oil Sands area of Alberta.